Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coordinating change implementation, monitoring and reporting on implementation, reviewing and closing ().
- A.change reason
- B.change model
- C.remediation plan
- D.change requests
正确答案及解析
正确答案
D
解析
变更管理通常由记录变更、评估所提出的变更的影响、成本、变更后的收益和风险、获得客户批准、管理和协调变更实施、监视和报告实施、回顾与关闭变更请求