某网络拓扑结构如下图所示:
在主机host1的命令行窗口输入tracert www.abc.com.cn命令后,得到如下结果:
C:\Documents and Settings\User>tracert www.abc.com.cn
Tracing route to caelum.abc.com.cn [208.30.1.101]
over a maximum of 30 hops:
1 1ms 1ms <1ms 119.215.67.254
<lms br="" style="box-sizing: border-box; -webkit-user-drag: auto !important; user-select: text !important;">2 2 ms 1 ms 1ms 172.116.11.2
3 71 ms 1ms 1ms 119.145.65.86
4 1ms 1ms 1ms 172.116.141.6
5 1ms 1ms 1ms 192.168.66.14
6 1ms 1ms <1ms 208.30.1.101
Trace complete.
则路由器router1 e0接口的IP地址为( ),www.abc.com.cn的lP地址为( )。
问题1选项
A.172.116.11.2
B.119.215.67.254
C.210.120.1.30
D.208.30.1.101
问题2选项
A.172.116.11.2
B.119.215.67.254
C.210.120.1.30
D.208.30.1.101
正确答案及解析
正确答案
解析
包含此试题的试卷
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案