以下施工网络图中,若节点0和6分别表示起点和终点,则关键路径为( )。
- A.0→1→3→6
- B.0→1→4→6
- C.0→1→2→4→6
- D.0→2→5→6
正确答案及解析
正确答案
解析
在一个网络图中有很多条路线,其中总长度最长的路线被称为关键路径。关键路径上的各事件为关键事件,关键时间的周期等于整个工程的总工期。有时一个网络图中的关键路线不止一条,即若干条路线长度相等,除关键路径外,其他路线被统称为非关键路线。
综上所述,四个选项中,选项C中的路径为关键路径。
包含此试题的试卷
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案