( )通过考虑估算中的不确定性与风险,使用三种估算值来界定活动期望完成工期的近似区间,可以提高活动成本估算的准确性。
- A.类比估算
- B.三点估算
- C.参数估算
- D.专家判断
正确答案及解析
正确答案
B
解析
三点估算通过考虑估算中的不确定性与风险,使用三种估算值来界定活动期望完成工期的近似区间,可以提高活动成本估算的准确性。
包含此试题的试卷
你可能感兴趣的试题
( )is the process of transforming information so it is unintelligible to anyone but the intended recipient.
-
- A.Encryption
- B.Decryption
- C.Security
- D.Protection
- 查看答案
As each application module is completed,it undergoes( )to ensure that it operates correctly and reliably.
-
- A.unit testing
- B.integration testing
- C.system testing
- D.acceptance testing
- 查看答案
( )algorithm specifies the way to arrange data in a particular order.
-
- A.Search
- B.Random
- C.Sorting
- D.Merge
- 查看答案
After analyzing the source code,( )generates machine instructions that will carry out the meaning of the program at a later time.
-
- A.an interpreter
- B.a linker
- C.a compiler
- D.a converter
- 查看答案
( )can help organizations to better understand the information contained within the data and will also help identify the data that is most important to the business and future business decisions.
-
- A.Data processing system
- B.Big Data analytics
- C.Cloud computing
- D.Database management
- 查看答案