Which of the following statement related to PMO is not correct? ()
- A.The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports
- B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO
- C.The PMO focuses on the specified project objectives
- D.The PMO optimizes the use of shared organizational resources across all projects
正确答案及解析
正确答案
C
解析
关于PMO的下列描述,哪一个是不正确的?A.PMO的特定形式、职能和结构依赖于它所支持的组织的需求。B.PMO的一个关键特性是在所有PMO管理的项目之间共享资源.C.PMO主要关注项目特定目标。D。PMO优化所有项目组织共享资源的利用。
你可能感兴趣的试题

-
- A.V(S2)和P(S4)
- B.P(S2)和V(S4)
- C.P(S2)和P(S4)
- D.V(S2)和V(S4)
- 查看答案

-
- A.V(S1)P(S2)和V(S3)
- B.P(S1)V(S2)和V(S3)
- C.V(S1)V(S2)和V(S3)
- D.P(S1)P(S2)和V(S3)
- 查看答案

-
- A.P(S4)和V(S4)V(S5)
- B.V(S5)和P(S4)P(S5)
- C.V(S3)和V(S4)V(S5)
- D.P(S3)和P(S4)V(P5)
- 查看答案

-
- A.P(S3)和V(S4)V(S5)
- B.V(S3)和P(S4)P(S5)
- C.P(S3)和P(S4)P(S5)
- D.V(S3)和V(S4)V(S5)
- 查看答案

-
- A.P(S2)和P(S4)
- B.P(S2)和V(S4)
- C.V(S2)和P(S4)
- D.V(S2)和V(S4)
- 查看答案