某项目各项工作的先后顺序及工作时间如下表所示,该项目的总工期为( )天。

- A.31
- B.32
- C.33
- D.34
正确答案及解析
正确答案
解析
本考题考查的知识点为关键路径法。
关键路径通常(但并非总是)是决定项目工期的进度活动序列。它是项目中最长的路径,即使很小的浮动也可能直接影响整个项目的最早完成时间。关键路径的工期决定了整个项目的工期,任何关键路径上的终端元素的延迟在浮动时间为零或负数时将直接影响项目的预期完成时间(例如在关键路径上没有浮动时间)。该项目有4条路径,其中ADFGI是关键路径,工期为32天。
包含此试题的试卷
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案