下图给出了一个信息系统项目的进度计划网络图(含活动历时)
下表给出了该项目各项活动的历时和成本估算值。
按照项目进度计划,第12天结束时应完成活动C、F、J,实际情况为:C完成了75%;F完成了100%;J完成了50%;实际花费25?000元。请计算该时点的计划值PV、挣值EV、成本绩效指数CPI和进度绩效指数SPI。(详细的解题步骤)
正确答案及解析
正确答案
解析
PV=1?000+2?000+4?000+3?000+4?000+2?000+3?000+2?000=21?000(元)EV=1?000+2?000+75%×4?000+3?000+100%×4?000+2?000+3?000+50%×2?000=19?000(元)CPI=EV/AC=19?000/25?000=0.76SPI=EV/PV=19?000/21?000=0.9
包含此试题的试卷
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案