Project work packages are typically
decomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, and
monitoring and controlling the project work.
- A.reviewing
- B.estimating
- C.auditing
- D.expecting
正确答案及解析
正确答案
B
解析
暂无解析