Which of the following statement related to PMO is not correct? ( )
- A.The specifiC form, function, and structure of A PMO is dependent upon the needs of the organization that it supports
- B.One of the key features of a PMO is managing shareD.resources across all projects administered by the PMO
- C.The PMO focuses on the specifie
- D.The PMO optimizes the use of shared organizational resources across all projects
正确答案及解析
正确答案
C
解析
下列各项中,哪一个有关PMO的说法是错误的? ()
A.PMO的具体形式、职能和结构取决于它支持的组织的要求
B.PMO的关键特征之一是在所有PMO管理的项目之间共享和协调资源
C.PMO关注于特定的项目目标
D.PMO对所管理的所有项目共享资源的使用进行优化
参考答案:C
你可能感兴趣的试题

-
- A.V(S2)和P(S4)
- B.P(S2)和V(S4)
- C.P(S2)和P(S4)
- D.V(S2)和V(S4)
- 查看答案

-
- A.V(S1)P(S2)和V(S3)
- B.P(S1)V(S2)和V(S3)
- C.V(S1)V(S2)和V(S3)
- D.P(S1)P(S2)和V(S3)
- 查看答案

-
- A.P(S4)和V(S4)V(S5)
- B.V(S5)和P(S4)P(S5)
- C.V(S3)和V(S4)V(S5)
- D.P(S3)和P(S4)V(P5)
- 查看答案

-
- A.P(S3)和V(S4)V(S5)
- B.V(S3)和P(S4)P(S5)
- C.P(S3)和P(S4)P(S5)
- D.V(S3)和V(S4)V(S5)
- 查看答案

-
- A.P(S2)和P(S4)
- B.P(S2)和V(S4)
- C.V(S2)和P(S4)
- D.V(S2)和V(S4)
- 查看答案