项目经理小李依据当前技术发展趋势和所掌握的技术能否支撑该项目的开发,进行 可行性研究。小李进行的可行性研究属于 ( ) 。

  • A.经济可行性分析
  • B.技术可行性分析
  • C.运行环境可行性分析
  • D.其他方面的可行性分析

正确答案及解析

正确答案
B
解析

从"依据当前技术发展趋势和所掌握的技术能否支撑该项目的开发"这句话判断为技术可行性研究。

你可能感兴趣的试题

单选题

( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.

  • A.Plan Quality Management
  • B.Manage Quality
  • C.Control Quality
  • D.Project Charter
查看答案
单选题

( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.

  • A.Plan Scope Management
  • B.Collection Requirements
  • C.Validate Scope
  • D.Control Scope
查看答案
单选题

The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).

  • A.technology management process
  • B.resource management process
  • C.quality management process
  • D.risk management process
查看答案
单选题

( )is a decentralized database,ensure that the data will not be tampered with and forged.

  • A.Artificial intelligence
  • B.Blockchain
  • C.Sensing technology
  • D.Big datA
查看答案
单选题

( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.

  • A.Cloud computing
  • B.Big datA
  • C.Blockchain
  • D.Internet of things
查看答案

相关题库更多 +