某项任务由子任务Ⅰ(计划编制和批准)和子任务Ⅱ(计划实施)组成。项目经理认为子任务Ⅰ的乐观历时为3天,最可能为4天,悲观历时为8天;子任务Ⅱ的乐观历时为5天,最可能6为天,悲观历时为10天。根据估算,该任务估算历时为 ( ) 天。
- A.10
- B.11
- C.12
- D.13
正确答案及解析
正确答案
解析
用三点估算法,估算活动平均时间为(乐观历时 + 4 ? 最可能历时 + 悲观历时)/6计算可得,子任务Ⅰ的平均时间为4.5天,子任务Ⅱ的平均时间为6.5天。因此该任务估算历时为“4.5天 + 6.5天 = 11天”。故选B。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案