某项任务由子任务Ⅰ(计划编制和批准)和子任务Ⅱ(计划实施)组成。项目经理认为子任务Ⅰ的乐观历时为3天,最可能为4天,悲观历时为8天;子任务Ⅱ的乐观历时为5天,最可能6为天,悲观历时为10天。根据估算,该任务估算历时为 ( ) 天。

  • A.10
  • B.11
  • C.12
  • D.13

正确答案及解析

正确答案
B
解析

用三点估算法,估算活动平均时间为(乐观历时 + 4 ? 最可能历时 + 悲观历时)/6计算可得,子任务Ⅰ的平均时间为4.5天,子任务Ⅱ的平均时间为6.5天。因此该任务估算历时为“4.5天 + 6.5天 = 11天”。故选B。

你可能感兴趣的试题

单选题

( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.

  • A.Plan Quality Management
  • B.Manage Quality
  • C.Control Quality
  • D.Project Charter
查看答案
单选题

( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.

  • A.Plan Scope Management
  • B.Collection Requirements
  • C.Validate Scope
  • D.Control Scope
查看答案
单选题

The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).

  • A.technology management process
  • B.resource management process
  • C.quality management process
  • D.risk management process
查看答案
单选题

( )is a decentralized database,ensure that the data will not be tampered with and forged.

  • A.Artificial intelligence
  • B.Blockchain
  • C.Sensing technology
  • D.Big datA
查看答案
单选题

( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.

  • A.Cloud computing
  • B.Big datA
  • C.Blockchain
  • D.Internet of things
查看答案

相关题库更多 +