己知某系统由A B C D E F六个活动构成,项目实习人员根据活动逻辑关系及历时等信息绘制了该系统的网络图,并给出了该系统的工期为9周,项目组其他成员纷纷提出意见。以下意见中( )是正确的。

- A.逻辑关系错误,项目工期应为7周
- B.有循环回路,项目工期是正确的
- C.节点序号编排不对,项目工期正确
- D.项目工期应为8周
正确答案及解析
正确答案
D
解析
暂无解析
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案