如果挣值EV是300万元,实际成本AC是350万元,计划值PV是375万元。进度执行指数显示:
- A.仅以原始计划速率的86%进行项目
- B.正在以原始计划速率的93%进行项目
- C.正在以原始计划速率的107%进行项目
- D.仅以原始计划速率的80%进行项目
正确答案及解析
正确答案
D
解析
SPI=EV/PV=300/375=0.8=80% 即仅以原始计划速率的80%进行项目
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案