下表给出了某信息系统建设项目的所有活动截止到2018年6月1日的成本绩效数据,项目完工预算BAC为30000元。

该项目的成本和进度执行情况()
- A.成本超支与进度滞后
- B.成本超支与进度超前
- C.成本节约与进度滞后
- D.成本节约与进度超前
正确答案及解析
正确答案
解析
PV=1000+1500+3500+800+2300+4500+2200+2500+4200+3000=25500元EV=1000+1500+3500+800+2300+4500*0.8+2200+2500*0.6+4200*0.5+3000*0.5=20000元AC=1000+1600+3000+1000+2000+4000+2000+1500+2000+1600=19700元CPI=EV/AC=20000/19700=1.02SPI=EV/PV=20000/25500=0.78
你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案