某项目由P1、P2、P3、P4、P5五个活动组成,五个活动全部完成之后项目才能够完成,每个活动都需要用到R1、R2、R3三种互斥资源,三种资源都必须达到活动的资源需求量,活动才能开始。已分配资源只有在完成本活动后才能被其他活动所用。目前项目经理能够调配的资源有限,R1、R2、R3的可用资源数分别为9、8、5。活动对资源的需求量、已分配资源数和各活动历时如下表所示(假设各活动之间没有依赖关系):

基于以上案例,请计算项目的完工时间为()
- A.4
- B.5
- C.6
- D.7
正确答案及解析
正确答案
解析

你可能感兴趣的试题
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
-
- A.Artificial Intelligence
- B.Cloud Computing
- C.Internet of Things
- D.Big Data
- 查看答案
In project human resource management , ( )is not a source of power for the project manager.
-
- A.referent power
- B.expert power
- C.reward power
- D.audit power
- 查看答案
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
-
- A.detail feasibility analysis
- B.opportunity analysis
- C.economic feasibility analysis
- D.risk analysis
- 查看答案
( )is a grid that shows the project resources assigned to each work package.
-
- A.Stakeholder engagement assessment matrix
- B.Requirements traceability matrix
- C.Probability and impact matrix
- D.Responsibility assignment matrix
- 查看答案
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
-
- A.digital
- B.networking
- C.intelligentize
- D.informatization
- 查看答案