题目详情

在项目实施中间的某次周例会上,项目经理小王用下表向大家通报了目前的进度。根据这个表格,目前项目的进度()

高级信息系统项目管理师,章节练习,基础复习,项目进度管理

  • A.提前于计划7%
  • B.落后于计划18%
  • C.落后于计划7%
  • D.落后于计划7.5%

正确答案及解析

正确答案
C
解析

在目前的监控点,该项目的挣值EV、PV及SPI如下:

EV=20000×90%+50000×90%+30000×100%

=93000

PV=20000+50000+30000

=100000

SPI=EV/PV

=93000/100000

=93%

落后于进度计划:1-93%=7%

你可能感兴趣的试题

单选题

Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.

  • A.Artificial Intelligence
  • B.Cloud Computing
  • C.Internet of Things
  • D.Big Data
查看答案
单选题

In project human resource management , ( )is not a source of power for the project manager.

  • A.referent power
  • B.expert power
  • C.reward power
  • D.audit power
查看答案
单选题

At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.

  • A.detail feasibility analysis
  • B.opportunity analysis
  • C.economic feasibility analysis
  • D.risk analysis
查看答案
单选题

( )is a grid that shows the project resources assigned to each work package.

  • A.Stakeholder engagement assessment matrix
  • B.Requirements traceability matrix
  • C.Probability and impact matrix
  • D.Responsibility assignment matrix
查看答案
单选题

Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.

  • A.digital
  • B.networking
  • C.intelligentize
  • D.informatization
查看答案

相关题库更多 +