一般而言,项目的范围确定后,项目的三个基本目标是 ( ) 。
- A.时间、成本、质量标准
- B.时间、功能、成本
- C.成本、功能、质量标准
- D.时间、功能、质量标准
正确答案及解析
正确答案
A
解析
项目的三个基本目标是:时间、成本、质量标准,在项目管理的背景下,范围这个术语可以有两种理解:
产品范围和项目范围。
而题干问的问题就是:项目范围的范畴的问题。
而功能是属于产品范围范畴的问题。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案