某公司中标一个企业信息化系统开发项目,合同中该项目包括:人事系统、OA系统和生产系统。下图为项目经理制作的WBS,此处项目经理违反了关于WBS的 ( ) 原则。

- A.WBS需要考虑将不同的人员的工作分开
- B.WBS中各项工作是为提供可交付成果服务的
- C.可以按照系统子系统来逐层分解 WBS
- D.一个工作单元只能从属于某个上层单元
正确答案及解析
正确答案
D
解析
"OA系统"与"人事系统下面都有""员工培训",这违反了WBS划分原则的"一个工作单元只能从属于某个上层单元"的原则。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案