在进行项目需求管理时,某需求的状态描述是"该需求已被分析,估计了其对项目余下部分的影响,已用一个明确的产品版本号或创建编号分配到相关的基线中,软件开发团队已同意实现该需求",则这个需求状态值是 ( ) 。
- A.已建议
- B.已验证
- C.已实现
- D.已批准
正确答案及解析
正确答案
D
解析

你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案