某工程包括A、B、C、D、E、F、G七项工作,各工作的紧前工作、所需时间以及所需人数如下表所示(假设每个人均能承担各项工作)该工程的工期应为 ( ) 天。

- A.13
- B.14
- C.15
- D.16
正确答案及解析
正确答案
解析
根据题意可画出带时标的双代号网络图如下图所示:

可识别出关键路径为:A—B—D—E—G工期为15天。调整非关键路径上的活动,使得 各路径上并行活动人数最少的方案如下图。

故该工程的工期应为15天。按此工期,整个工程最少需要7人。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案