在项目实施期间的某次周例会上,项目经理向大家通报了项目目前的进度。根据以下表格特征,目前的进度 ( ) 。

- A.提前计划7%
- B.落后计划15%
- C.落后计划7%
- D.提前计划15%
正确答案及解析
正确答案
解析
PV=20000+30000+50000=100000EV=20000*0.9+30000*0.9+50000=93000SPI=93000/100000=0.93因为SIP<1所以进度落后,(1-0.93)*100%=7%故答案为C。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案