某项目由ABCDE五个活动构成,完成各活动工作所需要的最可能时间Tm、最乐观时间To、最悲观时间Tp见下表:

各活动之间的信赖关系如下:

则该项目工期的估算结果约为 ( ) 天。
- A.22
- B.23
- C.24
- D.25
正确答案及解析
正确答案
解析
先找出关键路径:关键路径是:1-3-5-6,求B,D,E 3个活动的最可能时间之和,B是(5×4+2+10)/6,D是(7×4+3+15)/6,E是(10×4+6+20)/6,3者相加等于24。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案