下图中活动“G”可以拖延____周而不会延长项目的最终结束日期。

- A.0
- B.1
- C.3
- D.4
正确答案及解析
正确答案
解析
试题分析本题可以依据网络图首先用顺推法,得出关键路径、项目总工期、每个活动的最早开始时间和最早完成时间,再用逆推法得到每个活动的最迟开始时间和最迟完成时间。最后,算出活动G的浮动时间。对本题而言,应注意虚活动增加的路径。本题的关键路径为D-H-C,项目总工期为12周,活动G所在的路径F-G有4周的浮动时间。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案