活动排序的工具和技术有多种,工具和技术的选取由若干因素决定。如果项目经理决定在进度计划编制中使用标准化的项目进度网络图,这可能因为 ( )
- A.该项目非常独特,在不同的阶段需要专门的网络图
- B.在现有网络上具有可以获取的资源管理软件
- C.在项目中包含几个相同或几乎相同的可交付成果
- D.项目中存在多条关键路径
正确答案及解析
正确答案
C
解析
用排除法。交付物相同或相近,可能项目的进程(各计划活动、工期等)也相近,使用标准化的网络图,能够事半功倍。
你可能感兴趣的试题
( )is that it provides guidance and direction on how quality will be managed and verified throughout the project.
-
- A.Plan Quality Management
- B.Manage Quality
- C.Control Quality
- D.Project Charter
- 查看答案
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.
-
- A.Plan Scope Management
- B.Collection Requirements
- C.Validate Scope
- D.Control Scope
- 查看答案
The information security management system preserves the confidentiality,integrity and availability of information by applying a( ).
-
- A.technology management process
- B.resource management process
- C.quality management process
- D.risk management process
- 查看答案
( )is a decentralized database,ensure that the data will not be tampered with and forged.
-
- A.Artificial intelligence
- B.Blockchain
- C.Sensing technology
- D.Big datA
- 查看答案
( )puts computer resources on the web,and must meet the requirements of super capacity,super concurrency,super speed and super security.
-
- A.Cloud computing
- B.Big datA
- C.Blockchain
- D.Internet of things
- 查看答案